Project Summary

Goodridge Corners Stage 4

Location
North Edmonton, AB
Client
City of Edmonton
Category
General Contracting
Duration
May 2026 – Current

As the General Contractor, WCL completed the site development including the following scopes of work:

  • Premobilization documents including Traffic Accommodation Plans, ECO Plans, Site Safety Plans, Project Hazard Assessment, Emergency Response Plans and scheduling
  • Earthworks activities related to residential lot and roadway grading
  • Installation of new storm and sanitary sewers and watermain to connect to the existing system and provide services to mixed use and residential lots
  • Construction of shallow utilities including gas, street lighting, power and tele-communications
  • Surface works construction of roads, sidewalks and bike paths, shared-use paths and pararamps
  • Landscaping of roadway boulevards and public green spaces including Public Utility Lots (PULs)
  • Installation, maintenance of Erosion and Sediment Control (ESC) measures and ESC reporting during construction and maintenance & warranty period until issuance of Final Acceptance Certificate (FAC)